|
A. LCC SUPPORT HYDRAULICS MAINTENANCE TASKS - ALL SERIES CONTROLS
|
|
These tasks involve required periodic maintenance on hydraulic components which affect the reliability of the speed control systems and therefore should
be addressed at the recommended intervals. These items are applicable to all LCC and non-LCC speed controlled feed pump turbines.
|
|
PM-200A-1 Servomotor LeakageTests (LP and HP where applicable)
|
|
Parts Renewals:
|
Servomotor Pilot and Pilot Bushing.
|
|
|
Service Period:
|
Servomotors should be tested for excess leakage every two years. Pilot replacements are not necessary of tests determine leakage within guidelines. Excess leakage in servomotors results in valve position instability and poor turbine speed control.
|
|
Post-Rebuild:
|
Dynamic x-y plot (Snitch) testing of control oil pressure to stroke function and response at five percent intervals. Response lag, excess hysteresis, and non-linearity issues addressed.
|
|
No Action Risk:
|
Servomotor oscillations causing turbine speed hunting and excess bushing wear. Feedwater control instability and possible trips due to low or high feedwater levels.
|
| |
|
PM-200A-2 Stop Valve Solenoid Operator Inspections/Renewals/Replacements
|
|
Parts Renewals:
|
Detent Snaps, O-rings, Spool, Spool Seals, Solenoids OR full unit replacements.
|
|
|
Service Period:
|
Solenoid Valves should be inspected every four years of operation. Full rebuilds of all active parts should be performed every eight years.
|
|
Inspection Points:
|
Key inspection items are detent hold forces, solenoid actuation forces, FME intrusion, and spool wear.
|
|
Post-Rebuild:
|
Solenoid actuation verifications, flow control verifications.
|
|
No Action Risk:
|
Failure to reset turbine.
|
| |
|
PM-200A-3
Stop Valve Pilot Operator Inspections/Renewals/Replacements
|
|
Parts Renewals:
|
Pilots, seals, O-rings OR full unit replacements.
|
|
|
Service Period:
|
Pilot Operated Valves should be inspected every four years of operation. Full rebuilds of all active parts should be performed every eight years.
|
|
Inspection Points:
|
Key inspection items are FME intrusion and spool wear.
|
|
Post-Rebuild:
|
Pilot actuation verifications, flow control verifications.
|
| No Action Risk:
|
Failure to operate stop valve.
|
| |
|
PM-200A-4
Autostop Oil Pressure Decay Test
|
|
Parts Renewals:
|
Determined by test.
|
|
|
Service Period:
|
EACH major outage.
|
|
Inspection Points:
|
Temporary instrumentation installed to observe autostop oil system during header pressure bleed down. Identifies non-conforming components requiring service
|
|
No Action Risk:
|
False turbine trips, difficult to diagnose.
|
|
Note: This test should be performed following shutdown at the start of the outage to identify exact components work required.
|
| |
|
PM-200A-5
Control Pipe and Oil Tube Flush
|
|
Parts Renewals:
|
None
|
|
|
Service Period:
|
Elevated temperature high-flow oil flushes are recommended to remove tubing deposits each ten years. Failure to remove deposits can result in accumulation of FME and contamination of control components.
|
|
Inspection Points:
|
Pipe and tube swabs, flush discharge sock examination.
|
|
Post-Rebuild:
|
Leak test
|
| No Action Risk:
|
Control component contaminations. Possible feedwater oscillations and turbine trips.
|
| |
|
PM-200A-6
Bearing Drain Pipe Renewal
|
|
Parts Renewals:
|
Bearing drain pipe flange gaskets, re-insulation
|
|
|
Service Period:
|
Ten years with low lube oil water content, five years with high.
|
|
Inspection Points:
|
Internal pipe corrosion levels.
|
|
No Action Risk:
|
Control component contaminations. Possible feedwater oscillations and turbine trips.
|
|
Note: Removal and off site pickling and coating process arranged for three-day turn around at outage start.
|
| |
|
PM-200A-7
Bearing Oil Orifice and Relief Valve Adjustment
|
|
Parts Renewals:
|
None
|
|
|
Service Period:
|
Each Outage
|
|
Inspection Points:
|
Relief Valve within Oil Reservoir
|
|
No Action Risk:
|
Incorrect oil balance, HP vs. Bearing Oil, possible low bearing oil trip, servomotor transient oil starvation.
|
|
Note: This is recommended as a post-shutdown, start of outage task.
|
| |
|
PM-200A-8
Thrust Bearing Cage Oil Retention Test
|
|
Parts Renewals:
|
Possible orifice change
|
|
|
Service Period:
|
Each Outage
|
|
Inspection Points:
|
Thrust Bearing Cage
|
|
No Action Risk:
|
Thrust bearing damage and turbine trip.
|
|
Note: This is recommended as a post-shutdown, start of outage task.
|
| |
|
PM-200A-9
Vapor Extractor Butterfly Valve Test/Adjustment
|
|
Parts Renewals:
|
None
|
|
|
Service Period:
|
Each Outage
|
|
Inspection Points:
|
Reservoir Vacuum
|
|
No Action Risk:
|
Water entry into oil system, corrosion contamination, feedwater oscillations and turbine trip.
|
| Back To Top |
|
B. LCC 200-SERIES WITH MAGTON E/H CONVERTERS
|
|
PM-200B-1 LPEHC E/H Converters
|
|
Parts Renewals:
|
Cup Valve, Cup Valve Seat, Valve Stem, Pivot Shoulder Screws, Linear Bearing, Diaphragm.
|
|
|
Service Period:
|
E-H Converters should be fully inspected every two years of operation. Full rebuilds of all active parts should be performed every six years.
|
|
Post-Rebuild:
|
Dynamic x-y plot (Snitch) testing of control oil pressure to stroke function and response at five percent intervals. Response lag, excess hysteresis, and non-linearity issues addressed.
|
|
No Action Risk:
|
Servomotor oscillations causing turbine speed hunting and excess bushing wear. Feedwater control instability and possible trips due to low or high feedwater levels.
|
| |
|
PM-200B-2 Flowpath Selection Valve Inspections, Testing
|
|
Parts Renewals:
|
Detent Snaps, O-rings, Spool, Spool Seals, Solenoids OR full unit replacements.
|
|
|
Service Period:
|
Flowpath Selection Valves should be inspected every four years of operation. Full rebuilds of all active parts should be performed every eight years.
|
|
Inspection Points:
|
Key inspection items are detent hold forces, solenoid actuation forces, FME intrusion, and spool wear.
|
|
Post-Rebuild:
|
Solenoid actuation verifications, flowpath verifications.
|
|
No Action Risk:
|
Flowpath mixing, possible inability to change flowpaths.
|
| |
|
PM-200B-3
Electrolytic Capacitor Review/Replacement
|
|
Parts Renewals:
|
Electrolytic capacitors of control modules and isolators. Full power supply replacements.
|
|
|
Service Period:
|
Electrolytic capacitor components should be replaced every ten to twelve years of service.
|
|
Inspection Points:
|
Engineering review of component schematics produces capacitor change checklist.
|
|
Post-Rebuild:
|
Power supply calibration and general electronics functional test.
|
| No Action Risk:
|
Component electrical failure, turbine shutdown.
|
| |
|
PM-200B-4
Speed Probe Alignment Inspection
|
|
Parts Renewals:
|
None
|
|
|
Service Period:
|
Speed probe alignment to the target wheel should be verified following each major maintenance inspection or thrust bearing adjustment. Failure to align speed probes can result in speed channel losses and control upsets.
|
|
Post Adjust:
|
Speed Channel integrity verification.
|
|
No Action Risk:
|
Speed Channel Malfunctions, potential loss of speed feedback control.
|
| |
|
PM-200B-5
Field Connector Inspections
|
|
Parts Renewals:
|
None
|
|
|
Service Period:
|
Depending upon conditions of service this should be performed every five to eight years on each system connector in the Signal Processor, Startup Station, and the Local Electronics Cabinets.
|
|
Inspection Points:
|
All multi-conductor connectors benefit from solvent cleaning and Stabilant 22 contact enhancer treatment.
|
| No Action Risk:
|
Speed control loss, turbine shutdown.
|
| |
|
PM-200B-6
Cabinet Ground Integrity Inspection
|
|
Parts Renewals:
|
Grounding Straps, Cables
|
|
|
Service Period:
|
Following any change in plant electrical ground status in the cabinet vicinity or every ten years as a general test.
|
|
Inspection Points:
|
Grounds are electronically measured and verified periodically to insure no loose connections or ground path impedance has been introduced.
|
|
No Action Risk:
|
Turbine speed transients with potential feedwater level trip. Difficult to diagnose.
|
|
Notes: Field cabinet grounds are essential to the defense against EMI/RFI intrusion and control upset.
|
| |
|
PM-200B-7
Hydraulic Transformer Inspection (Applicable units only)
|
|
Parts Renewals:
|
Cup Valve, Cup Valve Seat, Bellows.
|
|
|
Service Period:
|
Hydraulic Transformers should be fully inspected every two years of operation. Full rebuilds of all active parts should be performed every six years.
|
|
Inspection Points:
|
Key inspection items are Cup Valve edge upsets, Cup Valve seat scratches or dents, bellows leaks and alignment.
|
|
No Action Risk:
|
Instability in COP, valve control oscillations.
|
| Back To Top |
|
C. LCC 200-SERIES WITH BADGER PNEUMATIC SPEED CHANGERS
|
|
PM-200C-1 Factory Badger Positioner Rebuilds
|
|
Parts Renewals:
|
Diaphragms, bearings, gaskets, o-rings, shafts, springs if needed.
|
|
|
Service Period:
|
Full rebuilds should be performed each plant cycle. Badger valve inventory should be maintained to permit change outs each outage.
|
|
Inspection Points:
|
Wear on shaft and bearings, Springs, all internal pieces.
|
|
Post-Rebuild:
|
Post-Rebuild: Dynamic x-y plot (Snitch) testing of demand to control oil pressure function and response at five percent intervals. Response lag, excess hysteresis, and non-linearity issues addressed.
|
|
No Action Risk:
|
Instability in COP, turbine speed control hunting, possible feedwater level trip if in service.
|
|
Notes: Recommended Pneumatic actuator and Hydraulic base servicing in tandem.
|
| |
|
PM-200C-2 Flowpath Selection Valve Inspections, Testing
|
|
Parts Renewals:
|
Detent Snaps, O-rings, Spool, Spool Seals, Solenoids OR full unit replacements.
|
|
|
Service Period:
|
Flowpath Selection Valves should be inspected every four years of operation. Full rebuilds of all active parts should be performed every eight years.
|
|
Inspection Points:
|
Key inspection items are detent hold forces, solenoid actuation forces, FME intrusion, and spool wear.
|
|
Post-Rebuild:
|
Solenoid actuation verifications, flowpath verifications.
|
|
No Action Risk:
|
Flowpath mixing, possible inability to change flowpaths.
|
| |
|
PM-200C-3
Electrolytic Capacitor Review/Replacement
|
|
Parts Renewals:
|
Electrolytic capacitors of control modules and isolators. Full power supply replacements.
|
|
|
Service Period:
|
Electrolytic capacitor components should be replaced every ten to twelve years of service.
|
|
Inspection Points:
|
Engineering review of component schematics produces capacitor change checklist.
|
|
Post-Rebuild:
|
Power supply calibration and general electronics functional test.
|
| No Action Risk:
|
Component electrical failure, turbine shutdown.
|
| |
|
PM-200C-4
Speed Probe Alignment Inspection
|
|
Parts Renewals:
|
None
|
|
|
Service Period:
|
Speed probe alignment to the target wheel should be verified following each major maintenance inspection or thrust bearing adjustment. Failure to align speed probes can result in speed channel losses and control upsets.
|
|
Post Adjust:
|
Speed Channel integrity verification.
|
|
No Action Risk:
|
Speed Channel Malfunctions, potential loss of speed feedback control.
|
| |
|
PM-200C-5
Field Connector Inspections
|
|
Parts Renewals:
|
None
|
|
|
Service Period:
|
Depending upon conditions of service this should be performed every five to eight years on each system connector in the Signal Processor, Startup Station, and the Local Electronics Cabinets.
|
|
Inspection Points:
|
All multi-conductor connectors benefit from solvent cleaning and Stabilant 22 contact enhancer treatment.
|
| No Action Risk:
|
Speed control loss, turbine shutdown.
|
| |
|
PM-200C-6
Cabinet Ground Integrity Inspection
|
|
Parts Renewals:
|
Grounding Straps, Cables
|
|
|
Service Period:
|
Following any change in plant electrical ground status in the cabinet vicinity or every ten years as a general test.
|
|
Inspection Points:
|
Grounds are electronically measured and verified periodically to insure no loose connections or ground path impedance has been introduced.
|
|
No Action Risk:
|
Turbine speed transients with potential feedwater level trip. Difficult to diagnose.
|
|
Notes: Field cabinet grounds are essential to the defense against EMI/RFI intrusion and control upset.
|
| Back To Top |
|
D. LCC 200-SERIES & SERIES-2 WITH EXLAR ELECTRIC ACTUATORS
|
|
PM-200D-1 Exlar Electric Actuator
Inspection/Maintenance
|
|
Parts Renewals:
|
Viton seals.
|
|
|
Service Period:
|
Three years under normal operating conditions.
|
|
Inspection Points:
|
Re-grease, check seals, roller screw fit check.
|
|
Post-Rebuild:
|
Valve stroke tests.
|
|
No Action Risk:
|
Excess actuator friction and roller screw wear.
|
| |
|
PM-200D-2 Flowpath Selection Valve Inspections, Testing
|
|
Parts Renewals:
|
Detent Snaps, O-rings, Spool, Spool Seals, Solenoids OR full unit replacements.
|
|
|
Service Period:
|
Flowpath Selection Valves should be inspected every four years of operation. Full rebuilds of all active parts should be performed every eight years.
|
|
Inspection Points:
|
Key inspection items are detent hold forces, solenoid actuation forces, FME intrusion, and spool wear.
|
|
Post-Rebuild:
|
Solenoid actuation verifications, flowpath verifications.
|
|
No Action Risk:
|
Flowpath mixing, possible inability to change flowpaths.
|
| |
|
PM-200D-3
Electrolytic Capacitor Review/Replacement
|
|
Parts Renewals:
|
Electrolytic capacitors of control modules and isolators. Full power supply replacements.
|
|
|
Service Period:
|
Electrolytic capacitor components should be replaced every ten to twelve years of service.
|
|
Inspection Points:
|
Engineering review of component schematics produces capacitor change checklist.
|
|
Post-Rebuild:
|
Power supply calibration and general electronics functional test.
|
| No Action Risk:
|
Component electrical failure, turbine shutdown.
|
| |
|
PM-200D-4
Speed Probe Alignment Inspection
|
|
Parts Renewals:
|
None
|
|
|
Service Period:
|
Speed probe alignment to the target wheel should be verified following each major maintenance inspection or thrust bearing adjustment. Failure to align speed probes can result in speed channel losses and control upsets.
|
|
Post Adjust:
|
Speed Channel integrity verification.
|
|
No Action Risk:
|
Speed Channel Malfunctions, potential loss of speed feedback control.
|
| |
|
PM-200D-5
Field Connector Inspections
|
|
Parts Renewals:
|
None
|
|
|
Service Period:
|
Depending upon conditions of service this should be performed every five to eight years on each system connector in the Signal Processor, Startup Station, and the Local Electronics Cabinets.
|
|
Inspection Points:
|
All multi-conductor connectors benefit from solvent cleaning and Stabilant 22 contact enhancer treatment.
|
| No Action Risk:
|
Speed control loss, turbine shutdown.
|
| |
|
PM-200D-6
Cabinet Ground Integrity Inspection
|
|
Parts Renewals:
|
Grounding Straps, Cables
|
|
|
Service Period:
|
Following any change in plant electrical ground status in the cabinet vicinity or every ten years as a general test.
|
|
Inspection Points:
|
Grounds are electronically measured and verified periodically to insure no loose connections or ground path impedance has been introduced.
|
|
No Action Risk:
|
Turbine speed transients with potential feedwater level trip. Difficult to diagnose.
|
|
Notes: Field cabinet grounds are essential to the defense against EMI/RFI intrusion and control upset.
|